Top Stories
Dreading the Delay


Owning a dream home is not as easy as it sounds. Despite the fat equated monthly installments draining one’s pocket every month, sometimes buyers fall prey to the devil of delayed possession due to manifold reasons.
According to survey by international property consultant Jones Lang LaSalle India (JLL), in terms of the average delay in delivering residential projects across India, more than 25 per cent of the committed supply has not been able to hit the market as per schedule.
“The National Capital Region’s performance in terms of delivery of residential supply due in 2013 has been the worst across all the major Indian cities. In Gurgaon, only one-third of the total committed supply for 2013 has been delivered so far. The situation has been even more alarming in other NCR regions such as Noida, where only about one fifth of the residential supply committed for delivery in 2013 has been delivered so far,”the JLL report said.
Many NCR-based developers such as Parsvnath, BPTP, lreo, Grand Arch, Vatika, Jaypee, Supertech, Orris and others are all set to complete their projects during 2014- 16. Although they are hopeful that they will meet their completion deadlines, the projects, it seems, may be delayed due to some reason or other. Among other things, due to the slow progress of their construction, the project completion may miss the deadline to some extent.
Though it is difficult to predict a project delay, bureaucrats in the sector feel that there must be an effective grievance redressal tool in the system to resolve such problems.
“It is true that at present there is no effective grievance redressal mechanism regarding delays of project. As far as the issue is concerned, it is not covered under HUDA jurisdiction,” said PC Meena, administrator, Haryana Urban Development Authority (H U DA).
A lot of hope is placed on the upcoming Real Estate Regulator Bill. “Once the real estate regulatory bill is passed and the regulator is in place, I think all these problems will be taken care of by the regulator,” said Praveen Kumar, commissioner, Municipal Corporation, Gurgaon.
On being contacted many realty companies like Supertech and Panchsheel, they declined to comment non the delayed possession issue while realty giant DLF is quite hopeful that this year will be a year of delivery for DLF.
• In terms of the average delay in delivering residential projects across India, more than 25% of the committed supply has not been able to hit the market as per schedule
• NCR’s performance in terms of delivering of residential supply due in 2013 has been the worst across all the major Indian cities. In Gurgaon, only one-third of the total committed supply for 2013 has been delivered so far. The situation has been even more alarming in other NCR regions such as Noida, where only about one-fifth of the residential supply committed for delivery in 2013 has been delivered so far.
Ananta Singh Raghuvanshi, executive director (Sales & Marketing), DLF Universal Ltd told Realty & More that internally DLF hastried its best to lay down proper systems and controls so that it can deliver on-time and live up to its commitments.
“But yes there have been some projects in the past which got delayed, some were delayed because of reasons beyond our control, for instance in Panchkula, where we were very well intended, we started our construction, work was going on at full pace, then suddenly due to the court case we were pushed back to one and a half years, may be more,” Raghuvanshi said, adding that DLF was trying its best to cut back on delays and give the possessions on time.
Asked about the specific reasons that lead to delayed deliveries, Raghuvanshi said: “Lack of trained manpoweris a reason for the delays. The whole industry is in a nascent stage. In real estate industry you have to train people on the job -for final registration documents, for taxation related issues, there is an audit process,possession process itself is so complicated, and in the transfer process, there are so many checks-and-balances, and then, at the time of handing over many people also want to exit.”
Says Ajay Singal, director, Avalon Group: “As the ongoing slowdown engulfs the real estate sector, delays are becoming the norm for the sector. However there are a variety of reasons for the delay. A developer needs to sell about 40-50 per cent of the apartments in the project to have enough cash to begin construction. Amid the current slowdown, achieving this target generally takes a longer time. The rising costs of materials and labour have further compounded the developers’ financial woes. During the meltdown, all economic activity also comes to halt. This generally leads to a long chain of delayed payments by many buyers.”
According to media reports, in the Delhi region, which attracts the maximum number of investors , the list of delayed projects includes those from well-known developers such as Unitech, Raheja Developers, DLF and the Jaypee Group.
Developers are not to be blamed for all delays. “For instance, projects have been stalled for over a year due to the Naida Extension land acquisition debacle. Projects have to be cleared by several government authorities and procuring clearances is a long-drawn process too,” said Santosh Kumar, CEO, Operations, Jones Lang LaSalle India.
Whatever be the reasons for delayed possessions, the Indian realty sector stands to gain substantially in terms of more business and also in enhancing its prestige if this problem is addressed.
WHY PROJECT DELAYS?
Poor project management is often one of them but this is not essentially the prime reason. In fact, it is the current economic scenario- defined by high levels of inflation and escalating construction costs- that is the leading reason for delayed projects. Developers are facing a severe liquidity crisis and donot have the capital to complete their projects. However, there are also other factors at play. Apartfrom all other reasons, one of the more important ones is dispute on the proposed land because of which the court may pass a stay order on the construction. For instance, buyers in the Naida Extension came to know about the land dispute only after it was reported by the media. Had they tried to find out, they could have come to know on their own.
Delay in regulatory clearances is another critical reason for delays in project deliveries. In many cases of delayed projects in Delhi NCR, the water and sand crises as well as environmental regulations which developers have not been able to meet have played a role. In quite a few projects, the lag caused by various bureaucratic processes has also been an operative factor in delayed project clearances.
What Babus Say?
PRAVEEN KUMAR, Commissioner, Municipal Corporation, Gurgaon
PC Meena, Administartor, HUDA
WARNING SIGNS
Buyers need to be alert to avoid the risk of getting locked in a delayed project. The builder is likely to offer possession on time if a project has necessary approvals along with funding from a bank. Several projects boast of 100 per cent funding from foreign private equities and other investors, which means delays are less likely for lack of funds.
REMEDY RECOURSE
Buyers have little say in booking agreements. The penalties for delay in payments by buyers are mentioned explicitly but obligations of timely delivery by builders are played down. Such lopsided agreements were common a few years ago. The draft real estate regulation bill, which proposes a sector regulator, seeks to outline the obligations of project delivery. Until regulations are put in place, buyers will have to rely on their rights laid out in their booking agreements.
CAREFUL INVESTING
Buyers looking for a home are the worst affected as they end up paying rent and interest on home loans. Investors are happy to see the prices of their property appreciate. So, the decision to seek refund or disposal of the property should be based on ground realities
What Developers Say
Satyendra Tomar, JMD, Proplarity Group
Ananta Singh Raghuvanshi, ED (Sales & Marketing), DLF Universal
Nitesh Kumar, COO, TDI Infracorp
P SAHEL, Vice-Chairman, Lotus Greens
ANUJ GOEL, ED, KDP Infrastructure
AJAY SINGAL, Director, Avalon Group
-
News6 days ago
Gaur City Mall Buzzes as Superstar Sunny Deol Promotes Latest Film ‘Jaat’
-
News2 weeks ago
April Shower: Real Estate Gets Booster Shot as RBI Cuts Repo Rate by 25 BPS
-
News2 weeks ago
RBI’s Second Consecutive Repo Rate Cut to 6% Spurs Optimism Across Real Estate Sector
-
News1 week ago
Vegas Mall Hosts Grand Event on April 13 to Celebrate the Spirit of Baisakhi
-
News7 days ago
Superstar Sunny Deol Visits VVIP Style Mall, Ghaziabad
-
Guest Column1 week ago
Look East: How Noida, Greater Noida are Poised to Ride India’s Retail Leasing Surge
-
News3 days ago
Manish Jain Takes the Helm as New President of CREDAI Pune Metro
-
News1 week ago
ANAROCK Appoints Vik Lulla to Lead US Commercial Leasing and Advisory Operations